Authorities report that the most technically challenging works on the 32-kilometer Kajaran-Agarak section of Armenia’s North-South Road Corridor have largely been completed, with the excavation of the tunnels finished and more than 90% of earthworks carried out.
According to the Road Department, overall construction progress currently stands at around 60%, and work on the strategically and economically important road section is actively underway.
“Its construction will significantly increase the volume of freight and passenger transportation, as well as traffic speed and convenience, which, in turn, will have a positive ripple effect on other sectors of the economy. The construction of the Kajaran-Agarak road section is one of the few projects being implemented in Armenia that incorporates almost all road infrastructure components simultaneously, including bridges, tunnels, overpasses, interchanges, and other artificial structures,” the agency said, noting that a significant amount of work is also being carried out to relocate and construct utility lines.
At this stage, work on infrastructure structures, including bridges, retaining walls, and the interior lining and finishing of tunnels, is continuing at a particularly active pace.
An average of around 645 workers and 228 units of various types of construction machinery are involved in the construction works.